At RMC, we understand the challenges you face. We have helped our clients achieve exceptional levels of manufacturing productivity and operational efficiency. These are explained below thru examples from manufacturing units where the process has been applied.

Change Management

Change Management

Example 3 -- From a Cement Plant - Change Management
Number of Plants under Reliability Improvement = 3
% Of equipment covered under Reliability Improvement Plan = 62 (most critical + critical)

Other benefits for the same plant:

• Seal failure analysis = presently no seal failure takes place
• Bearing failure analysis = presently no unwanted/premature bearing failure takes place
• Bearing selection = redesign for bearing that were giving inadequate life
• Gear failure analysis = presently no undesirable gear failure takes place
• Lubrication/WDA/Tribology = Lubricant cost brought down by 67%
• Heat exchanger study = No heat build up for any of the critical machines
• Vibration analysis = Accuracy of analysis increased to 98%
• Spare parts management = Reduction in the cost of spares thru lesser use
• Identification of training needs and SOP (Standard Operating Procedure)= Implemented for better operability and maintenance

Innovation Management

Innovation Management

The yield of a continuous casting plant (Stand Pig Casting Machine) could not be improved beyond 92 to 93% by any of the available improvement theories and techniques, like TPM (thru JIPM), Theory Of Constraints, TOP (McKinsey model), TBEM, TQM and Six Sigma etc with 4 years of continuous effort. However with the application of Design Out For Reliability (DOFR), the yield increased to 98% plus in barely three months with minimum effort, giving the company additional profit increase by 8% on a continuous basis (the reported profit margin of the company is around Rs. 35 crores).

Quality Improvement

Quality Improvement

Quality Improvement through DOFR

The yield of a continuous casting plant (Stand Pig Casting Machine) could not be improved beyond 92 to 93% by any of the available improvement theories and techniques, like TPM (thru JIPM), Theory Of Constraints, TOP (McKinsey model), TBEM, TQM and Six Sigma etc with 4 years of continuous effort. However with the application of Design Out For Reliability (DOFR), the yield increased to 98% plus in barely three months with minimum effort, giving the company additional profit increase by 8% on a continuous basis (the reported profit margin of the company is around Rs. 35 crores).

Strategy & Leadership

Strategy & Leadership

With sound understanding of the varied problems existing withing the working structure of the organization we are able to render excellent services pertaining to apt strategy and motivational leadership. The service has proved to be highly fruitful for many industrial companies.
Signature Projects Consulting Practice Training Programs (In-company and Public seminars) Case Studies Change ManagementInnovation ManagementQuality ImprovementStrategy & Leadership

View Showcase

Please take a quick tour of our Showcase & sample some of our exclusive offers.

Play Now

Highlights

National Conference
We held a National Conference on...

view all.. read more..

Hot Offers

Factory Design and Architecture
Factory Design and Architecture

Member IndiaMART.comCopyright © Reliability Management Consultant, All Rights Reserved (Terms of Use)
Site Developed by IndiaMART InterMESH Limited